Technical Data
Initial Set Time ASTM C807 45 minutes
Compressive Strength ASTM C579B 2 hours 4000 psi
28 days 7640 psi
Shear/Bond Strength ASTM C882 28 days 1566 psi
Chloride Permeability ASTM C1202 14 days 1498 coul
Dry Shrinkage ASTM C596 28 days .0907%
Coverage
One 5-gallon pail will cover approximately 16 square feet at a thickness of 1/4 inch.
Preparation
Roughen the edges for proper adherence and remove all loose debris. If area has grease or oil build up use brush with detergent and water to clean. Flush with water to eliminate any detergent residue. Allow area to remain damp but with no puddles.
Directions
Mixing: Add 5 parts of dry mix to 1 part clean water and mix thoroughly.
CPM requires much less water than other concrete products. The mix will appear dry at first, but will “moisten” as mixing continues. If the initial set starts, DO NOT add more water and try to remixor retemper, as this will result in loss of strength. Application: Place mixed material in the dampened area to be patched. Work material into the old concrete and trowel finish.
For Best Results
After the initial set has taken place, the surface may be moistened and troweled to a smooth finish. For maximum strength, cure the surface by keeping it damp for 24 hours. If repair is deeper than 6” apply in 2 equal layers waiting 30 minutes between applications.
Safety
Wear protective clothing (gloves and safety glasses) as direct contact may irritate eyes and skin. Wash exposed areas promptly with water. If any material gets into the eyes, rinse immediately and contact a physician.